Water Districts

Town Water Districts

If you need assistance finding funding to connect water to your home, download and view this form.

June 1, 2020
All water main on Town and County roads have been completed. These areas have been hydro seeded as part of the preliminary restoration to prevent erosion. Disturbed blacktop on roads and driveways has been repaired. The crew encountered heavy rock as they tried to bore under Tunnery Brook on Route 238 so our contractor (Randsco Pipeline) and our engineers (Mountain Engineering) are working with DEC to find an acceptable solution for the crossing. The two sections that remain to be completed, are the Railroad crossings on Attica Rd. and Town Line Ext.

Water main is now being installed on Route 20 starting at the Village of Alexander line and working west.

At the water tank site sub-contractors have stripped the area where the tank will set and it passed the test to ensure that the ground can hold the weight of the water tank. They will continue to prepare the site for the tank foundation. Verizon also moved a fiber optic cable that was located near the tank foundation site to the Route 20 right of way. Another sub-contractor has installed conduit for the generator pad. They will be pouring the concrete pad for the generator in June and continue electrical construction.

May 4, 2020
The water main contractor, Randsco Pipeline, has completed installation on Alexander Darien Town Line Road. The water main installation on Bowen Road continues and will take roughly a week to complete. Construction along Gillate Road has resumed and should be complete this coming week. The crews will start installing the main line on Route 238 at Darien Townline Rd. and progress towards the Village of Attica. If a second crew is available water main installation on Attica Rd. will occur at the same time.

Directional drilling for various locations has begun and is currently progressing in the Route 238 and Attica Road area.

Construction for the water storage tank by Statewide Aquastore is scheduled to begin the second week in May.

April 14, 2020
The water main contractor, Randsco Pipeline, has completed installation on Goodman and Stannard Roads. Construction along Alexander Darien Town Line Road continues. The water main installation will likely be completed up to Route 238 in another week. The contractor will proceed to Bowen Road which will be closed, but limited to local traffic only, for an estimated 3-5 weeks. Construction along Gillate Rd will temporarily stop, while that crew goes to Elba's project for a few weeks to finish restoration there.

Blue flags will be distributed by representatives of the Town's engineer to the property owners as construction nears their property. These flags should be placed to mark the location of the new service. The inspectors will be available to answer any questions. Tentative construction for the water storage tank by Statewide Aquastore may begin in May and be completed by the end of June.

March 27, 2020
Construction for Water District No. 5 started Tuesday, March 17th and Randsco Pipeline, Inc. recently finished the water main installation on Goodman Road. Pressure testing and health samples will be taken at a later date. The Contractor will continue heading west on Stannard Road. Stannard Road will be closed, but limited to local traffic only for an estimated 3-4 weeks. Gillate Road will be the next road; it is estimated that Gillate Road will take an additional 3-4 weeks. Updates will be provided on this website indicating where construction will continue following the water main installation of these roads.

March 17, 2020
Construction for Water District No. 5 is scheduled to begin on Tuesday, March 17th. The contractor, Randsco Pipeline, Inc. will be starting the water main installation at Goodman Road and Route 98. The contractor will continue on Goodman Road to Stannard Road and then Gillate Road. Goodman and Stannard Roads will be closed, but limited to local traffic only for an estimated 5-8 weeks. It is estimated that the water main installation along Gillate Road will take an additional 2-3 weeks. Updates will be provided on this website indicating where construction will continue following the water main installation of these roads.

June 1, 2020
The next step in the formation of water district #6 is to take a petition door to door to have residents of the water district sign if they are in favor of forming the district. Those opposed do not sign the petition. We will need at least 50% of resident property owners assessed valuation and at least 50% of all property owners assessed valuation of the district to sign to move forward with the district. We have the petition ready but decided in light of the COVID-19 pandemic to wait to go out and ask for signatures. We will be setting up training by our attorney and engineer for petition carriers. If you are interested in being a petition carrier for Water District #6 contact Shannon at 585-591-2455 and we will let you know the time and date of the training session.